Based on the initiative of Pakistan Cables Limited, Multan Electric Power Company (MEPCO) completed their ACCC conductor installation in Pakistan with the support of EPC Contractor NETRACON Technologies by upgrading the 132 kV “NGPS to Industrial Estate” transmission line.
ACCC Helsinki size conductor was selected for re-conductoring the 5-kilometer transmission line that replaced existing ACSR Coyote size conductor. This effectively raised the system capacity from 300 to 700 amps, without the need to modify the right-of-way or existing structures.
The installation work was completed by M/s NETRACON Technologies (Pvt.) Limited under the technical supervision of the CTC Global Certified Master Installer.