The National Electric Power Regulatory Authority (NEPRA) released an inquiry report on major power breakdown in the country on Tuesday. On January 9, several parts of the country, including Islamabad, Karachi and Lahore, had suffered a massive power breakdown.
As per the report, Guddu Power Station tripped at 11.41pm due to human error. “Though development work was underway at the station, SOPs were completely neglected, which resulted in a massive breakdown.” The officials responsible for not taking steps for improvement in the National Transmission and Dispatch Company’s (NTDC) system were also named. The actions which were supposed to be taken were neglected, the report read.
The NEPRA in its recommendations to avoid such incidents in the future has urged for vast study for energy saving. The authority has urged to take precautionary measures to avoid power breakdowns in the future. NTDC, K-Electric and other power plants have been directed to put precautionary measures in place. Provision of electricity should be ensured in case of any emergency-like situation.